Arlington Heights Park District Photo
Arlington Heights Park District
Arlington Heights Park District Photo

Pioneer Park Community Center Update - January 2007

The Pioneer Community Center construction progressed well in December. Almost every construction milestone necessary for a January 2, 2008 opening were met by the end of the month. The community center opened to the public on the morning of January 2. The front reception desk and the folding wall in Activity Room B and C are the final pieces to be completed on the interior project.  Additional landscaping, tennis court and basketball court improvements will also be completed in the spring.  Punch list repair items and corrections continue.

Programs are running at Pioneer Park Community Center. The office officially opens Monday, January 7. The office will be open Monday-Friday, 1-5 PM and Saturdays, 9 AM-Noon.

Don't miss the Grand Opening/Open House February 23. Watch for details!

Pioneer Park Community Center Update - December 2007

With the start of December, ceiling and lighting installation is in progress. Interior painting is still in progress, floor tile and carpeting installation is in progress, casework installation is in progress, door and window installation along with numerous other interior items are in progress.

Park District staffs are completing purchases prior to building opening for Pioneer Community Center operational items not included in the construction managers scope.

Pioneer Park Community Center Update - November 2007

Pioneer Community Center construction progressed well in November. Many construction milestones necessary for a January 2008 opening have been met this month including gym and dance room floor installation, washroom floor and wall tile, plumbing fixture installs, interior painting and HVAC work and drywall installation. Landscaping improvements were completed and the playground was opened to the public.

 

 


500 S. Fernandez Av.
Arlington Heights, IL 60005

View photos from the construction site. Pioneer Project Construction Photos

Plans approved for Construction:

Elevations
1 | 2 | 3 | 4

Floor Plan

Site Plan

Board Meeting Agendas & Minutes
Pioneer Park Community Center Update - October 2007

Pioneer Community Center construction progressed well in September.   Many construction milestones necessary to be completed for a January 2008 opening have been met this month including completion of flat roofing, concrete curbs, tennis court and parking lot bases, numerous concrete paths, playground site preparation and curbing, window frame installation, tennis court and parking lot light fixture installation. 
 

With the start of October, we will expect to see the completion of masonry, landscaping, playground installation, barrel vault roof installation, pathway installation, parking lot and tennis court installation, window installation along with numerous other interior items.  From this point forward, the weather is now our enemy.

Questions regarding the project may be directed to Brian Huckstadt, Director of Parks and Planning 847-577-3009 or bhuckstadt@ahpd.org.

Pioneer Park Community Center Update - March 21, 2007

The Pioneer Park Community Center construction project is well underway. Site and building demolition was completed prior to January 1, 2007 and the building pad was prepared for installation of footings and foundations in early January. However, the extremely cold temperatures late this winter kept workers from pouring footings and foundations until the first week of March when the weather finally moderated.

Weather permitting, and that is always the case in early spring, precast walls of the gymnasium are scheduled for installation the week of March 26. Roof trusses for the gymnasium and general masonry will follow immediately thereafter. As the spring months progress, the site will be prepared for the opening of the swimming pool and athletic field activities. As part of the preparation, just prior to the Memorial Day weekend, the main entry roadway from Grove Street will be reopened to the public to accommodate swimming pool and athletic field pickup and drop-off.

At the same time the main entry roadway reopens to the public, a 45-50 car portion of the ‘new’ parking lot will be made available for public use. Construction fencing currently in place will be relocated to the East to accomplish this goal. Tennis and basketball courts will remain closed at Pioneer this summer and fall.

At this time, staff is preparing to open the new Pioneer Park Community Center for programming and public use during the first week of January 2008.

 
Pioneer Park Community Center Project  - November 6, 2006

On September 18, 2006 the Arlington Heights Village Board approved a request submitted by the Arlington Heights Park District to construct a new Pioneer Park Community Center and related park site improvements. Pioneer Park is located at 500 S. Fernandez, Arlington Heights IL 60005.

The Demolition Phase of this project has been approved by the Park Board and startup is currently awaiting receipt of Village and Cook County permits. In preparation, construction fencing has been installed and the Northeast quadrant of the park will be closed to the public, until further notice, on Monday November 6, 2006. Construction is anticipated to begin shortly thereafter.

Bids for the Construction Phase of the project will be opened on November 8, 2006 at 2 PM local time. Bidding documents and information are available by contacting B and H Industries, 80 W. Seegers Rd. Arlington Heights, IL, phone number is 847-593-3161. There is a refundable fee of $100 per bid packet. Following bid opening and review, park district staff and construction manager will prepare a recommendation to accept the lowest responsive, responsible bids to the Park Board at an upcoming Park Board meeting.

Questions regarding the project design or project details may be directed to Brian Huckstadt, Director of Parks and Planning 847-577-3009 or bhuckstadt@ahpd.org.

Pioneer Project Update - September 13, 2006

The Arlington Heights Village Board will hearing a request submitted by the Arlington Heights Park District for a new Pioneer Park Community Center and related Site Improvements. The location of the park property is at 500 S. Fernandez, Arlington Heights IL 60005.

This public meeting is open to all interested individuals and will be held at the Arlington Heights Senior Center, 1801 W. Central Road, Arlington Heights, Illinois, at 8:00 p.m., on Monday, September 18, 2006.

If you have questions related to upcoming Village of Arlington Heights actions on this project, please contact the Planning Department at 847-368-5200. Questions regarding the project design or project details may be directed to Brian Huckstadt, Director of Parks and Planning 847-577-3009 or bhuckstadt@ahpd.org.

Pioneer Project Update - July 25, 2006

A Public Hearing of the Village of Arlington Heights Plan Commission has been scheduled for the following purpose:

  • To amend the underlying Planned Unit Development ordinance to allow construction of a 22,700 square foot multi-purpose community building at Pioneer Park.
  • To approve a special use to allow a 22,700 square foot Community Center, Recreation Building (Municipal or Non-Municipal) in a P-L, Public Lands District.
  • To approve a variation from Chapter 28, Section 11.4 Schedule of Parking Requirements, to allow a reduction to the minimum parking stalls from 669 to 115 stalls.

The location of the property is at 500 S. Fernandez, Arlington Heights IL 60005

This hearing is open to the public and comments from the public on the proposal are invited. Hearing on said petition will be held by the Arlington Heights Plan Commission at the Arlington Heights Senior Center, 1801 W. Central Road, Arlington Heights, Illinois, at 7:30 p.m., on Wednesday, August 9, 2006.

The Village of Arlington Heights requires that a notice of this meeting shall be mailed to adjacent properties located within 250' of Pioneer Park and signage installed at each corner of the park.

Pioneer Project Update - April 13, 2006

Park District consultants presented Design Development plans for the Pioneer Community Center Project to the Park District Board of Commissioners on April 11, 2006. The Board of Commissioners approved the Design Development plans as presented and the consultants were directed to begin construction drawings. As approved, the Community Center building square footage will be approximately 22,700 square feet and the suspended walking track, (estimated to cost $500,000) has been removed from the project scope.

Park District staff have submitted Design Commission materials for an upcoming public meeting date, to be established by the Village. Plan Commission public hearing will also be arranged by the village. Per Village of Arlington Heights requirements, notice of the upcoming public hearing will be mailed to all property owners within 250 feet of the park perimeter and signage will be posted at two locations within Pioneer Park. A notice will also be posted on this Web site.

Pioneer Project Update - February 9, 2006

Park District staff presented the Schematic Design Phase of the Pioneer Community Center Project to the Plat & Sub Committee of the Village of Arlington Heights Plan Commission on February 8, 2006. The meeting was the first step in the Village review process and was not a public hearing. The project was presented as approved by the Park Board on January 10, 2006. Initial comments at the February 8 meeting from the Plan Commissioners were very positive with specific comments directed at on-site parking concerns.

With this meeting complete, Park District staff will assemble the required Plan Commission and Design Commission submittal materials for a future public hearing date, to be established by the Village. Per Village Plan Commission requirements, notice of the upcoming public hearing will be mailed to all property owners within 250 feet of the project and signage will be posted at two locations within Pioneer Park. A notice will also be posted on this Web site.

Pioneer Project Update - January 11, 2006

The Park Board approved the schematic design for the Pioneer Park Community Center Project at their January 10, 2006 Regular Board meeting. The architect will now begin the design development stage of the project. Staff will present the schematic design to the Village of Arlington Heights and begin the Village review process. The Village requirement sequence includes reviews by the Plat & Sub Committee; the Design Commission; the Plan Commission; and final approval by the Village Board. The dates of these reviews have yet to be determined.

There were modifications made from the conceptual plans that the Park Board approved on October 25, 2005. As the conceptual plans were further defined in schematic design, it became apparent the cost to construct such a building exceeded the budget. The major changes in the revised plans were:

  1. the elimination of the first floor meeting room;
  2. relocating the two second floor program rooms to the ground level;
  3. elimination of the second story of the building.

The building has been reduced from 31,972 to 28,085 square feet. The proposed suspended walking track is still under consideration, but might have to be eliminated due to cost. The fate of the walking track feature will be determined at the end of the Design Development stage. Should the suspended track be eliminated, the size of the building becomes 22,692 square feet. The Design Development stage is expected to be finalized by early to mid March.

Check out Pioneer Park Project's FAQ questions and answers.

Comments/Questions about The Pioneer Project may be directed to Brian Huckstadt, Director of Parks and Planning at 847-577-3009.


410 N. Arlington Heights Road • Arlington Heights, IL 60004 • 847-577-3000 • comments@ahpd.org
©1998-2008 Arlington Heights Park District