Green Slopes Park Capital Project

The Board of Commissioners approved moving forward with the redesign of the Green Slopes Tennis Courts at the Board meeting on June 23, 2020.  Staff worked with an engineering firm to re-design the tennis courts to include two tennis and 4 pickle ball courts.  Construction began May 10, 2021 and the site was open for play by August 27, 2021.  The walks leading to the courts were also reconstructed to allow for accessibility.  An official grand re-opening will take place later this summer.   

downloadPDFView Concept Rendering

What's Next?

Click on the green Construction below to follow our progress.  The anticipated timeline for the project is the following:

  • Design and permitting - Summer 2020 Check_Mark 
  • Bidding - Spring 2021  Check_Mark 
  • Construction - Summer 2021  Check_Mark 
  • Open - 3:00 PM August 27, 2021   Check_Mark
  • Grand Re-Opening Saturday, September 25 Public Invited! Check_Mark